KCLAD Wells Weekly Update: Key Points
1. Current Production
• Output: Two wells (#5 and #6) are producing a total of 350 gallons per minute (GPM).
• Water Depth: Approximately 84 feet.
2. Well Inventory
• Active Wells: #5 and #6.
• Pump Details: Submersible pumps set at 105 feet.
3. Future Development
• Wells #3 and #4:
• Pumps were removed last week.
• Challenge: High water depth (63 feet) prevents pump submersion.
• Plan: Use a 1-inch tube inserted into the casing for water extraction.
• Monitoring Upgrade:
• Ordered a test ultrasonic meter for Well #5.
• Includes Wi-Fi capability for instant notifications and real-time extraction results.
4. Additional Data
• Weekly well readings are maintained in attached spreadsheet.